AMP Project timeline

Key Phases of the project
AMP Project Key Dates
Phase/Activity Time Period
Phase 1 Design September 2011 to March 2012
Phase 1 Construction March 2012 to September 2012
Phase 2 to 4 Briefing September 2011 to December 2011
Phase 2 to 4 Design January 2012 to December 2012
Phase 2 to 4 Procurement January 2013 to May 2013
Phase 2 Enabling Works October 2012 to May 2013
Phase 2 Decant Space Creation May 2013 to November 2013
Phase 2 January 2014 to January 2015
Phase 3 Decant Space Modifications March 2015 to May 2015
Phase 3 April 2015 to April 2016
Phase 4 June 2016 to January 2017
Department of Aeronautics move and Completion February 2017 to March 2017