Category: Liquid-hydrogen System

22l of liquid hydrogen; a milestone for MICE and a cross-campus success for STFC

The international Muon Ionization Cooling Experiment (MICE) on ISIS at RAL has established stable operation passing a muon beam through a 22l volume of liquid hydrogen. Operating with this volume of liquid hydrogen is a major technical challenge and is the culmination of several years work by personnel from Technology Department (RAL and DL), PPD and ISIS.

Muon beams are produced from the decay of pions captured from the debris that arises when a proton beam strikes a target. When produced in this way, an intense muon beam occupies a large volume in three-dimensional “physical space” and a large volume in six-dimensional “phase space”; such a beam is said to have a large emittance.

Muon beams of low emittance have been proposed as the basis of powerful facilities for the study of fundamental particles. To create such beams requires that the muon-beam emittance be reduced very quickly; in a time short compared to the lifetime of the muon (2.2 microseconds). At production, a bunch of muons from the beam occupies a volume comparable to that occupied by a water melon and is highly divergent. To accelerate and manipulate the beam requires that the size of the bunch transverse to its direction of motion be reduced such that, after cooling, the bunch occupies a volume comparable to that of a cucumber.

The MICE collaboration seeks to demonstrate that ionization cooling can deliver the required cooling effect. In an ionization-cooling channel the beam is passed through a material (the absorber) in which it loses energy and is subsequently accelerated. Liquid hydrogen is expected to give the best cooling performance. A systematic study of the factors that determine the ionization-cooling performance of a section of accelerator that contains an absorber composed of liquid hydrogen is therefore a critical step in the successful execution of the MICE experiment.

The MICE liquid-hydrogen absorber is filled by condensing hydrogen gas. The condensation rate is such that it takes roughly one week to fill the 22l volume of the absorber vessel. The vessel was filled for the first time late in the evening of the 25th September 2017. This success was the culmination of years work by personnel from Technology Division (RAL and DL), PPD and ISIS. The absorber vessel was designed and built at KEK in Japan. The detailed design of the 120micron thick aluminium windows was carried out by the Project Engineering Group at RAL and the University of Oxford. The windows were fabricated in the USA.

To make the system work required a full system-engineering approach that was guided by M.Hills, A.Nichols, S.Watson, M.Courthold, T.Bradshaw and later by V.Bayliss and J.Boehm all of Technology Department at RAL and M.Tucker of PPD. The critical control system was delivered by P.Warburton from the Electrical Engineering Group in Technology Department at DL. The DL Control Systems and Safety Interlocks Group made critical contributions to the integrated safety-engineering approach that was adopted from the outset and delivered through a close collaboration between personnel from Technology and ISIS Departments. Personnel from the Particle Physics Department provided the “mission need” and M.Tucker, supported by S.Balashov, delivered the critical vacuum and gas-handling systems.

For the MICE collaboration establishing stable operation with liquid-hydrogen is a major milestone that allows the critical study of the factors that determine the ionization-cooling effect to be carried out. For STFC the successful completion of the liquid-hydrogen system demonstrates the strength of the cross-campus, inter-disciplinary collaboration necessary to deliver such a technically-demanding project.

Plot showing liquid hydrogen filling the MICE absorber.

Spokesman’s Update

Liquid-Hydrogen System

Last week, the absorber, condenser and associated pipe work were cooled to operating temperature.  Over the weekend, Josef Boehm, Mark Tucker and Phil Warburton brought the H2 liquefaction system into operation.  Liquid is now being condensed steadily and the absorber fill has begun.  It is estimated that around 1.5 l of liquid has been accumulated so far.  The status (“shifter” and “expert” panels) is shown below.

This is an important step!  The LH2-fill rate is a little slower than expected making it necessary to revise the block-diagram run plan.  The revised plan will be presented at tomorrow’s Operations Meeting.  The likelihood is that it will be necessary to advance “LH2 empty” data taking to exploit the time during which the absorber is filling.

Data Taking: Cycle 2017/02

Under the leadership of Paolo Franchini, MOM for the first part of the Cycle, the experiment has been brought into operation.  The readout has been tested successfully.  Melissa Uchida has devised, and implemented, the waveguide-swaps for the tracker.  A first re-calibration of the VLPCs has been carried out, a second calibration will take place today.  Over the weekend, David Adey refreshed the spare AFE boards; the boards are “live spares” for the tracker readout.  Finally, Alan Bross and Sandor Feher have brought the spectrometer solenoids up.  The magnets have been run at the currents required for the first configuration that will be used in the Cycle.

Decay Solenoid

The decay solenoid has been recommissioned.  It has been shown to be operational.  At present there is a gremlin in the interlock chain that defeats remote operation.  The fault is being addressed.

Conferences: COOL17 and NuFACT17

The new material presented at the recent video conferences has been finalised.  MICE talks at COOL17 (Dimitrije Maletic, Melissa Uchida) will take place at COOL today.  The contributions to NuFact (Francois Drielsma, Chris Hunt, John Nugent and Jaroslaw Pasternak) will follow next week.

Liquid-hydrogen System Commissioning

The third and final test of the liquid-hydrogen system using neon was successful. The test ended last Thursday (03Aug17) and the system was allowed to warm up over the weekend. The warm-up has been slow, indicating excellent thermal installation.

The outstanding work that must be carried out before the final safety inspection includes the completion of the remedial work on the hydrogen-quench line, the installation and inspection of ATEX-rated fittings in the LH2 shed on the roof of then MICE Hall and the completion of the safety-related paper work. In addition, the leak testing in the hydrogen-gas panel has to be repeated to document the (low and satisfactory) leak rates. The liquid-hydrogen team is working steadily to address the last remaining issues.

The final safety tour is scheduled for 17Aug17. Assuming the system is signed off as safe to operate, the commissioning of the system with hydrogen will commence as soon after the tour as possible.